Electrical · Load Estimation

Power Demand Calculator

Calculate Smarter. Work Faster.

Estimated demand load from total connected load and demand factor — the standard first step in sizing a panel, feeder, or transformer.

Power Demand Details

Enter total connected load and the applicable demand factor.

Calculation Mode

Use the first mode when the connected load is already known. Use the second to build it up appliance by appliance and get energy and running cost alongside demand.

Appliance / Load Schedule

Duty % is the share of the running hours the load actually draws power. A refrigerator compressor may be rated 150–800 W but cycles on roughly a third of the time, so 24 h/day at 30% duty is the honest figure — this is the main reason nameplate arithmetic overstates a bill.

Energy & tariff

Commercial and industrial tariffs bill this monthly on peak demand, separately from energy.

How many hours a day the demand load would run at full output to give the same energy. Used for the energy and cost figures in this mode.

Demand Load = Connected Load × DF kWh = W × h × duty ÷ 1000 Cost = kWh × tariff Load Factor = avg kW ÷ peak kW
Demand Load

Enter values and hit calculate

Demand Factor Used
Connected Load
Monthly Energy
Monthly Cost
What this means

Enter the load data to see how demand, energy and cost relate.

Breakdown

Enter values above to see a breakdown.

Did this solve your problem?

Created by Umasankar Maity — B.Tech in Electrical Engineering, with 11+ years of industrial maintenance experience.

Reviewed by the ElectroMechCalc editorial team.

Last reviewed: September 2026  |  References: standard demand-factor load estimation practice (IS 732 / NEC Article 220 style), and appliance energy figures cross-checked against equipment rating plates and energy labels.

How it works

How Demand Load Is Calculated from Connected Load

If you added up the nameplate rating of every piece of electrical equipment in a typical facility and wired the system to handle that full total simultaneously, you'd end up with dramatically oversized (and expensive) panels, feeders, and transformers — because in real operation, equipment doesn't all run at full rated load at the same instant. Demand factor is the standard tool for translating a facility's total connected load into a realistic demand load: the figure actually used to size electrical distribution equipment.

Formula used: Demand Load (kW) = Connected Load (kW) × Demand Factor. Demand factor is always a number between 0 and 1 (or equivalently, 0% to 100%) — a demand factor of 0.5 means the system is expected to draw, at its peak, about half of the total connected nameplate load.

Worked example: a facility has 500 kW of total connected load (summing the nameplate rating of all lighting, motors, HVAC, and other equipment), and based on its occupancy type and load mix, a demand factor of 0.5 is applied. Demand Load = 500 × 0.5 = 250 kW. This 250 kW figure, not the 500 kW connected load, is what's used to size the incoming service, main panel, and any upstream transformer — sizing to the full 500 kW connected load would be substantially oversized and unnecessarily costly.

Where demand factor values come from: demand factors published in wiring codes (IS 732 in India, NEC Article 220 in the US) are derived from decades of accumulated real-world metering and usage data across many similar facilities — they aren't arbitrary rules of thumb, but statistically grounded figures for how a given category of load actually behaves in practice. Different load categories have very different demand factors: continuous lighting circuits often have a demand factor close to 1 (since once turned on, lighting tends to stay on for the full occupied period), while a large population of motors or receptacle circuits typically has a much lower demand factor, since it's statistically unlikely all of them draw peak current simultaneously.

The category-by-category method (the more rigorous approach): for a complete, code-compliant electrical design, connected load is typically broken into standard categories — general lighting, receptacle outlets, motors, HVAC, kitchen/special equipment — and each category's own connected load is multiplied by its own specific demand factor from the applicable code table, then the resulting demand loads for each category are summed to get the total facility demand load. This is more accurate than applying one blended demand factor to the entire connected load, especially for facilities with a load mix that doesn't match a single "typical" category well (like a facility that's mostly continuous-process motor load with a small amount of office lighting).

Demand load and transformer/service sizing: once total facility demand load is calculated, standard practice adds a margin for future growth (commonly 15-25%) before selecting the actual transformer capacity or utility service size, since sizing exactly to today's calculated demand leaves no room for facility expansion, added equipment, or measurement uncertainty in the original connected load figures. The combination of demand factor (converting connected load to realistic demand) and a growth margin (providing headroom for the future) together determine the practical capacity a facility's electrical infrastructure should be designed around.

Summary: use Demand Load = Connected Load × Demand Factor for a quick, defensible estimate of the electrical capacity your system actually needs to be sized against, source demand factor values from the applicable code table for your specific load category rather than a generic assumption, use the category-by-category method for final design accuracy, and add a separate growth margin on top of the calculated demand load before finalizing transformer or service capacity.

Whether you're doing an early feasibility estimate or a final code-compliant design, the same underlying question drives every step: not how much equipment is connected, but how much of it is realistically expected to run at once — that distinction, captured by demand factor, is what separates efficient, appropriately-sized electrical infrastructure from an unnecessarily oversized and expensive installation.

Demand factor versus actual metered performance: demand factor tables are statistically representative but not a guarantee for any single specific facility — once a facility is operating, its utility bills (which typically show metered maximum demand) provide real, facility-specific data that can and should be compared against the original design-stage demand load estimate. A significant, sustained gap between calculated and actual metered demand (in either direction) is worth investigating: consistently lower actual demand might indicate an opportunity to right-size future expansions more efficiently, while consistently higher actual demand than the design estimate could indicate the original demand factor assumption was too optimistic for this specific facility's actual usage pattern.

How demand factor calculations feed into other electrical design steps: the demand load figure calculated here is typically the starting point for several downstream calculations — feeder and service conductor sizing (which must carry the demand load safely, following the same ampacity derating principles used elsewhere), transformer kVA sizing (after converting kW demand load to kVA using the system's expected power factor), and utility service application sizing (many utilities require an estimated maximum demand figure as part of a new service or upgrade application). Getting the demand load calculation right early in a project avoids costly redesign later if an undersized service or transformer is discovered only after connected load is finalized.

Worked Example

Connected load 500 kW, demand factor 0.5: Demand Load = 500 × 0.5 = 250 kW. This is the figure used to size the incoming service and main distribution equipment, not the full 500 kW connected load.

This calculator applies a single demand factor to a total connected load figure for a quick estimate — a complete electrical design typically breaks connected load into separate categories (lighting, receptacles, motors, HVAC, kitchen equipment, etc.), each with its own demand factor from the applicable code table, then sums the resulting demand loads. For final panel, feeder, or service sizing, follow the detailed category-by-category method in the applicable wiring code (IS 732 / NEC Article 220) rather than relying on a single blended demand factor alone.

Reference Table

Typical Demand Factors by Load Category

Load Category Typical Demand Factor
General lighting (dwelling/office, first portion)1.00 (first ~3000 VA), tapering thereafter
General-purpose receptacle outlets0.40-0.50 for loads beyond the first bracket
Single largest motor1.00 (full nameplate + margin, per code)
Additional motors beyond the largest0.65-0.80, decreasing with more motors
HVAC (multiple staged units)0.65-0.85
Kitchen/commercial cooking equipment0.65-0.80 depending on equipment count
Overall facility (mixed commercial/industrial)0.45-0.65 typical blended range

These figures are general, illustrative ranges — the applicable wiring code's actual table (IS 732 or NEC Article 220, depending on jurisdiction) provides the specific, code-mandated demand factors for each category and load bracket, which should always be used for a final, compliant design rather than these general ranges. Note how motor demand factor typically applies at 100% to the single largest motor (a conservative rule since that motor could genuinely run at full load at any moment) but drops for additional motors, reflecting the reduced statistical likelihood that every motor runs at full load at exactly the same moment.

For a facility with a genuinely unusual load profile that doesn't fit neatly into standard categories — a specialized industrial process, an unusual mix of continuous and intermittent equipment — the code-tabulated demand factors are still the required starting point for a compliant design, but actual metering of a comparable existing facility (if available) can provide a valuable sanity check against the tabulated estimate before finalizing equipment sizing.

The distinction that matters

kW Demand and kWh Energy Are Two Different Bills

Most electricity calculators answer only one question: how many units will this consume. That is the energy side, measured in kWh, and it is what a domestic bill is built on. But the transformer, the cable, the breaker and — on any commercial or industrial tariff — a large slice of the bill itself are sized by something else entirely: the peak demand in kW, the most you draw at any one moment.

The two behave nothing alike. A 7 kW EV charger running four hours a night and a 1.2 kW immersion heater running 23 hours both consume roughly 28 kWh a day, so their energy bills match. But one needs a supply nearly six times larger than the other. That is why this calculator reports both, from the same input.

Demand load (kW) = Connected load (kW) × Demand factor Energy (kWh) = Power (kW) × Running hours × Duty cycle Load factor = Average load ÷ Peak demand

Load factor ties them together. It is the average load divided by the peak, and it tells you how well you are using the capacity you pay to have available. A site at 20% load factor is renting a connection that sits idle four fifths of the time; the cheapest saving there is usually shifting load away from the peak rather than consuming less. A site at 75% is already using its connection well, and real savings have to come from consumption.

Where the demand charge bites. Industrial and commercial tariffs bill a monthly charge on the highest demand recorded — often on a 15 or 30 minute average, and in many tariffs ratcheted so that one bad half-hour sets the charge for months. Two motors started together instead of staggered can cost more over a year than either one runs up in energy. Enter your demand charge in the calculator and it splits the monthly figure so you can see which half you are actually paying.

Reference

Appliance Wattage and Duty Cycle

Wattage tables are everywhere; what they usually leave out is the column that decides your bill. A refrigerator's compressor may be rated 200 W, but it does not draw 200 W for 24 hours — it cycles. Multiply the nameplate by the clock and you will overstate a fridge by roughly three times. The duty cycle column below is the correction, and it is why the calculator asks for it on every line.

LoadTypical running powerTypical duty while onNotes
Air conditioner (split, 1.5 ton)1,200–1,800 W40–60%Inverter units modulate; fixed-speed units cycle hard
Refrigerator150–800 W25–35%Compressor cycles; door use and ambient raise it
Electric water heater1,500–3,000 W50–70%Thermostat-controlled, big morning peak
Ceiling fan50–80 W100%BLDC types run 25–35 W
LED lamp5–20 W100%Replaces a 40–100 W incandescent
Microwave oven800–1,500 W100%Short runs; input exceeds the cooking-power rating
Electric kettle1,500–2,200 W100%High power, very short duty
Washing machine350–2,000 W50–70%Peak only while heating water
Clothes dryer2,000–4,000 W85–100%Heat pump models draw far less
EV charger (home AC)3,300–7,400 W100%Usually the largest single demand in a house
Desktop computer100–300 W50–80%Idle draw is well below the PSU rating
Induction motor, 1 HP≈ 750 W output, ~900 W input60–90%Input exceeds output by the efficiency

Indicative planning figures, not manufacturer data. Check the rating plate or an energy label for the specific model, and note that a motor's nameplate states output power — the input it draws from the supply is higher by its efficiency and is what the meter records.

Running cost

Working Out What a Load Costs to Run

Energy is power multiplied by time, and cost is energy multiplied by the tariff:

kWh per day = Watts × hours/day × (duty % ÷ 100) ÷ 1000 Cost per month = kWh per day × 30.44 × tariff

Worked example. A 1.5 ton split air conditioner drawing 1,500 W, used 8 hours a night, cycling at 50% duty: 1,500 × 8 × 0.5 ÷ 1000 = 6 kWh a day. Over an average month that is 183 kWh, and at ₹8 per unit, about ₹1,460 a month. Run the same machine 12 hours at 60% duty and it becomes 10.8 kWh a day — ₹2,630 a month, from the same appliance.

Why the calculator uses 30.44 days. A month is not four weeks. Using 30 days understates an annual figure by about 5 days' consumption; 30.44 is the average calendar month (365 ÷ 12) and keeps the monthly and annual numbers consistent with each other.

Days per week matter too. A workshop machine running 8 hours a day, 5 days a week is not the same as one running every day. The calculator averages part-week loads back over the week rather than pretending they run daily, which is where simple wattage tables quietly inflate an industrial estimate.

Units

W, kW, kWh, BTU/h, Horsepower and Tons

The one distinction worth getting right: watts and kilowatts are power — a rate, how fast energy is being used. Kilowatt-hours are energy — a quantity, power sustained over time. A 2 kW heater does not use "2 kW an hour"; it uses 2 kWh in an hour. Meters bill energy; supplies are sized on power.

UnitIn wattsWhere you meet it
1 kW1,000 WSI multiple; nearly all electrical ratings
1 BTU/h0.2931 WAir conditioning and heating capacity, US market
1 ton of refrigeration3,517 W (≈ 12,000 BTU/h)AC and chiller capacity in India and the US
1 mechanical horsepower745.7 WMotor output ratings, US and India
1 metric horsepower (PS)735.5 WEuropean motor and engine ratings
1 kWh3.6 MJ ≈ 3,412 BTUThe billed unit of energy

A trap worth naming. An air conditioner's "1.5 ton" or "18,000 BTU" figure is its cooling capacity, not its electrical input. A 1.5 ton unit removes about 5.3 kW of heat while drawing perhaps 1.5 kW from the supply, because it moves heat rather than generating it. Entering 1.5 ton as the electrical load in any calculator will overstate that machine by roughly three times — for the meter, use the input power from the rating plate. The same applies to a motor: a 10 HP nameplate is shaft output, and the input is higher by the efficiency.

Reducing the bill

Cutting Demand Is Not the Same as Cutting Energy

Because the bill has two halves, so does the saving — and the actions are different.

To cut energy (kWh): start with whatever runs longest, not whatever is largest. A 9 W LED replacing a 60 W incandescent that burns 6 hours a day saves more over a year than switching off a 2 kW kettle you use for three minutes. Heating and cooling dominate most bills, so a thermostat setpoint moved one or two degrees, a serviced filter and a sealed duct usually beat any appliance swap. On motors, efficiency class and correct sizing matter: a motor loafing at 30% load runs at poor efficiency and poor power factor.

To cut demand (kW): stagger, do not shrink. Interlock the geyser against the oven, stagger motor starts so they do not coincide, and move batch loads — EV charging, pumping, compressed air top-up — outside the site's peak window. On a ratcheted demand tariff a single simultaneous start can set a charge you then pay for months, so the interlock is worth more than the equipment it protects.

Then check what you are being billed for. Poor power factor raises the kVA demand without raising kWh, so the correction capacitor bank pays back on the demand charge alone. Look at a real interval-meter profile before spending: the load curve tells you whether your problem is a tall peak or a wide base, and those two problems have opposite solutions.

Use this calculator for the arithmetic and the ranking, then verify against an actual meter reading before committing to capital spend. Estimated wattages and duty cycles are a starting point, not a measurement.

Common Mistakes

Common Mistakes When Calculating Power Demand

1. Using demand load figures to select equipment that must handle full connected load. Some individual components (like a large motor's own branch circuit conductor and starter) must still be sized for that specific piece of equipment's own full rated load, not a diversified system-wide demand load — demand factor applies to sizing shared/upstream equipment (main panels, feeders, transformers), not every individual branch circuit.

2. Applying a generic demand factor without checking the applicable code table. Demand factors vary meaningfully by load category, occupancy type, and jurisdiction-specific code — using a single remembered "typical" figure instead of the correct table entry for your specific load category and code edition can meaningfully misstate the true demand load.

3. Confusing demand factor with power factor or load factor. These are three distinct concepts despite similar-sounding names — demand factor relates connected load to expected peak demand for sizing purposes, power factor relates real to apparent power, and load factor relates average to peak demand over a billing period. Using one where another is required gives a nonsensical result.

4. Applying demand factor twice (once per category, then again to the total). If you've already calculated demand load category by category (lighting demand + motor demand + HVAC demand, each already using its own demand factor), summing those figures gives the total facility demand load directly — applying an additional blended demand factor on top of that sum double-counts the diversity effect and understates true demand load.

5. Not revisiting demand factor as a facility's load mix changes significantly. A facility that adds a large new continuous load (like server/data center equipment) after its original design will typically see its actual demand factor rise, since continuous loads have a demand factor much closer to 1 than the intermittent loads a blended factor originally assumed — failing to reassess can lead to an under-sized system once the new load is added.

6. Ignoring future growth when applying demand factor for initial sizing. Sizing distribution equipment exactly to today's calculated demand load, with no spare capacity margin, leaves no room for facility growth or added equipment — standard practice typically adds a growth margin (commonly 15-25%) on top of the calculated demand load when selecting transformer and main panel capacity, distinct from the demand factor calculation itself.

7. Forgetting to add a growth margin on top of the calculated demand load. Demand factor gives today's realistic demand estimate, but sizing equipment exactly to that figure with zero spare capacity leaves no room for facility growth or future load additions — standard practice adds a separate growth margin (commonly 15-25%) when selecting the actual transformer or service capacity.

8. Not comparing design-stage demand load estimates against actual metered demand once operational. A demand factor calculation is a statistical estimate, not a guarantee for your specific facility — once metered data is available, comparing it against the original design estimate helps validate (or correct) assumptions for future expansion planning.

FAQ

Frequently Asked Questions

What is the difference between kW and kWh? +

kW is power — the rate at which energy is used at a given instant, and what the cable, breaker and transformer are sized for. kWh is energy — power sustained over time, and what the meter bills. A 2 kW heater does not use "2 kW an hour"; it uses 2 kWh in an hour. Two loads with identical monthly kWh can need very different supply capacity, which is why this calculator reports both.

How do I calculate the running cost of an appliance? +

kWh per day = watts × hours per day × duty cycle ÷ 1000, then multiply by 30.44 for an average month and by the tariff for the cost. A 1,500 W air conditioner used 8 hours a night at 50% duty uses 6 kWh a day, about 183 kWh a month, which at ₹8 per unit is roughly ₹1,460. Leaving the duty cycle out of that calculation would double the answer.

Why does my refrigerator cost less to run than its wattage suggests? +

Because the compressor cycles. A fridge rated 200 W only draws that while the compressor runs, typically 25–35% of the time, so 24 hours a day at 30% duty is about 1.4 kWh rather than the 4.8 kWh a straight wattage × hours calculation gives. Thermostatically controlled loads — fridges, water heaters, air conditioners, room heaters — all behave this way, which is why the duty cycle field appears on every line of the schedule.

Can I enter an air conditioner in tons or BTU? +

You can, but be careful what the figure means. A unit's ton or BTU/h rating is its cooling capacity, not its electrical input: a 1.5 ton unit removes about 5.3 kW of heat while drawing perhaps 1.5 kW from the supply, because it moves heat rather than making it. Entering 1.5 ton as an electrical load overstates that machine roughly threefold. Use the input power from the rating plate, and keep the ton and BTU/h options for loads where the rating really is the power drawn.

What is load factor and what is a good value? +

Load factor is the average load divided by the peak demand over the same period, and it measures how well the connection you pay for is actually used. A low figure — under about 30% — means capacity sitting idle most of the time, and the cheapest saving is usually shifting load off the peak rather than consuming less. A high figure means the connection is well used and savings must come from consumption. There is no universally correct value: a continuous process runs high by nature, a single-shift workshop runs low.

What is a demand charge and how do I reduce it? +

Commercial and industrial tariffs bill a monthly charge on the highest demand recorded, often as a 15 or 30 minute average and frequently ratcheted so one bad half-hour sets the charge for months afterwards. You reduce it by staggering rather than shrinking: interlock large heating loads against each other, sequence motor starts so they never coincide, and move batch loads outside the peak window. Correcting power factor also helps where the charge is billed on kVA, since it lowers demand without changing kWh.

What is the formula for demand load? +

Demand Load (kW) = Connected Load (kW) × Demand Factor. Demand factor is the ratio of the maximum demand a system is likely to draw to the total connected load of all equipment, expressed as a decimal (or percentage) always less than or equal to 1 (100%).

Why is demand load almost always less than connected load? +

Because not every piece of connected equipment operates at its full rated load simultaneously — lighting might all be on, but motors cycle on and off, HVAC compressors stage rather than all running at once, and receptacle loads are rarely all drawing maximum current at the same moment. Demand factor captures this real-world diversity in usage, so a facility doesn't need to be wired and equipped for the theoretical (and rarely occurring) scenario where everything runs at full rated load at once.

What's the difference between connected load and demand load? +

Connected load is the sum of the nameplate (rated) capacity of every piece of electrical equipment in a facility, added together with no adjustment. Demand load is the realistic maximum load the system is actually expected to draw, after applying demand factors that account for diversity in when different equipment actually operates — demand load is what's used to size feeders, panels, and transformers, not the larger connected load figure.

Where do demand factor values come from? +

Demand factors are published in the applicable electrical wiring code (IS 732 in India, NEC Article 220 in the US, or similar) as tables organized by occupancy type and load category, based on decades of accumulated real-world usage data across many similar facilities. Using a code-published demand factor for your specific load category, rather than an arbitrary guess, ensures your sizing calculation is both defensible and code-compliant.

Can demand factor be greater than 1 (100%)? +

No, not under the standard definition — demand factor is always less than or equal to 1, since demand load can never exceed connected load (you can't draw more current than what's physically connected and capable of drawing). A calculated demand factor above 1 indicates either a measurement error or a misunderstanding of which figure is connected load and which is metered/measured demand.

How is demand factor different from diversity factor? +

These are related but distinct concepts often confused. Demand factor (used in this calculator) is the ratio of a single system's maximum demand to its own total connected load. Diversity factor is used when combining multiple separate demand loads (e.g., several different panels or feeders) into one larger system total, accounting for the fact that different sub-systems also don't hit their own individual peaks at exactly the same moment — diversity factor is typically greater than or equal to 1 and divides (rather than multiplies) the sum of individual demand loads.

Should I use a single blended demand factor or category-by-category demand factors? +

A single blended demand factor is useful for a quick, early-stage estimate, but a complete, code-compliant design should break connected load into standard categories (lighting, receptacles, motors, HVAC, special equipment) and apply each category's own specific demand factor from the applicable code table, then sum the resulting demand loads — this is more accurate than a single blended factor, especially for facilities with an unusual mix of load types.

Does demand factor change as a facility grows or its load mix changes? +

Yes — demand factor is a function of how equipment is actually used, not a fixed physical property, so a facility that adds a large continuously-running load (like data center equipment) will generally see a higher blended demand factor over time, while adding many intermittently-used loads (like additional receptacle circuits) tends to lower it. Periodically re-checking demand factor against actual metered maximum demand is good practice for a facility that has grown or changed significantly since its electrical system was originally sized.

Is demand load the same figure a utility bills against? +

Not necessarily — this calculator estimates demand load for electrical system design/sizing purposes (panels, feeders, transformers), which is a planning figure based on connected load and code-tabulated demand factors. A utility's billed maximum demand is typically the actual metered peak (see the Maximum Demand Calculator), which reflects real historical usage rather than a design-stage estimate, and the two figures, while related, often differ once a facility is actually operating.

Explore More Categories